For the general City permit, its paperwork and its fees, see structural repair permits in New Orleans. This page covers only the extra layer a historic district adds. We read the City and National Park Service pages cited below on October 29, 2026.
Two commissions, two areas
The Historic District Landmarks Commission regulates changes to the exterior of buildings in the City’s local historic districts. Its FAQ says there are eighteen local districts: fourteen residential districts under the New Orleans HDLC and four downtown districts under a separate Central Business District HDLC. The City’s district page lists Algiers Point, Bywater, Canal Street, Carrollton, Esplanade Ridge, Faubourg Marigny, Garden District, Holy Cross, Irish Channel, Lafayette Square, Lower Garden District, Mid-City, Parkview, Picayune Place, St. Charles, Treme, Uptown and the Warehouse District. The FAQ also notes there are twenty-one National Register districts and that the boundaries often overlap. A National Register listing is not the same thing as a local district.
The Vieux Carré Commission regulates the French Quarter. The City says its jurisdiction covers all private and semi-private properties in the Vieux Carré Historic District as defined by the state constitution. The VCC’s guidelines describe the original 1936 area as bounded by Iberville Street, Esplanade Avenue, North Rampart Street and the Mississippi River, and note that the local and National Historic Landmark boundaries differ slightly.
Not every local district is regulated the same way. The HDLC’s introduction (dated January 2019) describes “full control” areas, where all exterior work visible from a public right-of-way except paint color and plantings must be submitted, and “partial control” areas, where its jurisdiction can be limited to things such as demolition, new construction, or review and comment. We could not read from the published chart which districts fall in which group, so ask staff.
How to check whether a house is in a district
- The HDLC’s landmarks and districts page has an interactive map of the districts and a downloadable list of designated landmarks. A building can be an individually designated landmark outside a district.
- The City’s Where Y’At address lookup, linked from the HDLC’s Certificate of Appropriateness page, returns zoning, district and service information for an address.
- The City’s structural permit page tells applicants to check whether the building is in a historic district or the French Quarter, and if so to get HDLC or VCC approval.
When a Certificate of Appropriateness is needed
The City says a Certificate of Appropriateness is required for work on the exterior of buildings in local historic districts, and that this includes “repairs, alterations, additions, demolition, relocation, new construction, and site work.” The HDLC’s FAQ says it has jurisdiction only over the exterior. The process starts with an online building permit application; the HDLC reviews it, and the building permit follows once the certificate is issued. The French Quarter works the same way in outline: the VCC’s guidelines say its approval is “necessary, but not sufficient” for a building permit, and that it has no jurisdiction over interior work.
The HDLC says it does not collect fees. Instead, the City adds a 50 percent surcharge to the permit fee for property in a local historic district, which the permit page describes as property subject to additional regulation by the VCC or HDLC. The HDLC’s certificate page says the surcharge also applies to the plan checking fee.
Staff review or commission review
Both commissions have three levels. Staff can approve maintenance, in-kind repair and restoration. An architectural committee looks at changes to a building’s exterior configuration and makes recommendations. The full commission makes the final decision on projects beyond staff authority, and at the HDLC it also hears requests to keep work that was done without approval. The HDLC’s certificate page says staff review normally takes three to five days, and its introduction says the committee and the commissions meet monthly. The HDLC also rates buildings as Significant, Contributing or Non-Contributing, and its introduction says the rating determines the level of review.
| Work | What the guidelines say | Where it comes from |
|---|---|---|
| Repairing a cracked pier, repointing pier mortar | Listed as routine maintenance. The masonry chapter says open joints in a brick pier may indicate settlement and recommends checking whether the wood structure above has shifted, then repointing with compatible mortar. | HDLC Exterior Maintenance and Masonry and Stucco chapters (January 2019); VCC Exterior Maintenance chapter |
| Stucco on brick piers and chain walls | Maintenance lists include applying stucco plaster to brick piers. The porch chapter says chain walls and piers are most typically brick with a protective stucco coating, and for porches and raised galleries it recommends a 2 to 3 foot vented stucco chain wall at the front and piers at the sides. | HDLC Exterior Maintenance and Porches chapters (January 2019) |
| Lattice and infill between piers | We found only a termite-prevention item: install siding, frames and latticework at least 6 inches above ground. We did not find a rule on enclosing the space between piers. | HDLC Exterior Maintenance chapter; VCC Exterior Maintenance chapter |
| Raising a building up to BFE plus 1 foot, or 3 feet above grade, whichever is greater | The HDLC “encourages” this as the limit. Its review table lists both staff and commission review for this row. | HDLC Storm Preparedness chapter (January 2019) |
| Raising higher than that, or raising a building with a raised basement | The review table lists “Commission appeal.” The chapter says the HDLC does not approve elevating buildings built with raised basements. | HDLC Storm Preparedness chapter (January 2019) |
What the HDLC says about raising a historic house
The Storm Preparedness chapter says elevation typically involves abandoning crawlspaces, raising the first floor, and either building a new foundation or extending piers. It warns that existing walls or piers may not be strong or stable enough to reuse, that stronger, non-traditional materials such as filled concrete block or cast-in-place concrete may be needed, and that it may be possible to mimic the original material with stucco, brick or masonry. It notes that the taller the elevation, the more foundation is exposed, that structural materials may need “sensitively-designed screening,” and that front stairs on houses close to the property line may be hard to keep in their original orientation.
One more point is easy to miss. The HDLC’s New Construction, Additions and Demolition chapter (June 2022) includes in its definition of demolition “the raising of an existing building to create habitable space that complies with the ceiling height requirements set forth in Sec. 26-196.” We did not read that section of the City Code and cannot tell you when it applies, but it is a reason to talk to staff before an elevation is designed.
The City’s own extra requirements for a whole-house elevation permit are on our permits page.
The National Park Service guidance
The National Park Service’s Guidelines on Flood Adaptation for Rehabilitating Historic Buildings (2021) apply the Secretary of the Interior’s Standards for Rehabilitation to flood risk. They are national, not specific to New Orleans, and the document says they are not codified as program requirements; the Standards are regulatory only for federally assisted projects and the federal tax credit program. Points relevant to a raised house:
- “Buildings can generally be elevated a nominal amount without a major impact on the property’s historic character.”
- “Establishing a universal standard or measurement for how high any given building can be elevated is not possible.”
- With some exceptions, “elevating a small building to a height approaching a full story will not meet the Standards for Rehabilitation.”
- “Foundation type (open vs. closed) may be prescribed by the local ordinance.”
- It recommends repairing structural deficiencies, “such as rotten sill plates and termite damage,” before beginning work, and advises against lifting a building “without first conducting a thorough inspection.”
If rot or termites are part of the picture, see structural wood rot and beam and sill repair.
If work starts without approval
The HDLC’s introduction says work completed without an approved certificate is subject to possible fines, removal and restoration, that it issues stop work orders, and that the owner must then apply to keep the work, which the commission can deny. Neglect is a separate issue: the HDLC says owners who let a building deteriorate can be cited for “demolition by neglect,” and the VCC’s examples of it include a foundation, pier, wall or beam that can no longer safely carry its load.
Questions to ask before work is designed
- Is the house in a local historic district, the French Quarter, or a landmark, and is the district full or partial control?
- Is the work visible from the street, and does that change whether the commission reviews it?
- Can staff approve this scope, or will it go to the committee or the commission?
- If the house is being raised, what is the Base Flood Elevation here, and does the planned height stay within the HDLC’s preferred limit?
- Who is applying for the certificate and the permit, and will I get copies? See questions before hiring a foundation contractor.
What we cannot tell you
- Whether your house is in a district, or whether its district is full or partial control. Use the City’s map and lookup, then confirm with staff.
- Whether a specific job, such as replacing piers out of sight under the house, needs a certificate. The guidelines we read do not say.
- What the commission will allow for lattice, infill or skirting between piers. We found no specific guideline.
- Your Base Flood Elevation, or how high your house could be raised.
- How long review will take for your project. Published times are for staff review of a complete application.
The guideline chapters we read are dated 2019 and 2022, and City pages change. Confirm current rules with the HDLC, (504) 658-7051, 1300 Perdido Street, 7th floor; the Vieux Carré Commission, (504) 658-1429, same address, by appointment; or the Department of Safety and Permits, (504) 658-7200. We are an information and referral site, not a contractor, engineer, architect or government body, and nothing here is legal or permitting advice.
Sources (14)
- City of New Orleans: Certificate of Appropriateness (HDLC)Read October 7, 2026
- City of New Orleans: Renovation (Structural) / Elevation PermitRead October 7, 2026
- City of New Orleans, HDLC: Landmarks and Districts (map and list)Read October 29, 2026
- City of New Orleans, HDLC: Frequently Asked QuestionsRead October 29, 2026
- City of New Orleans, HDLC Design Guidelines ch. 1: Introduction (January 2019)Read October 29, 2026
- City of New Orleans, HDLC Design Guidelines ch. 4: Exterior Maintenance (January 2019)Read October 29, 2026
- City of New Orleans, HDLC Design Guidelines ch. 7: Masonry and Stucco (January 2019)Read October 29, 2026
- City of New Orleans, HDLC Design Guidelines ch. 9: Porches, Galleries and Balconies (January 2019)Read October 29, 2026
- City of New Orleans, HDLC Design Guidelines ch. 13: Storm Preparedness and Resilience (January 2019)Read October 29, 2026
- City of New Orleans, HDLC Design Guidelines ch. 12: New Construction, Additions and Demolition (June 2022)Read October 29, 2026
- City of New Orleans: Vieux Carre CommissionRead October 29, 2026
- City of New Orleans, Vieux Carre Commission Design Guidelines ch. 1: Introduction (2015)Read October 29, 2026
- City of New Orleans, Vieux Carre Commission Design Guidelines ch. 3: Exterior Maintenance (2015)Read October 29, 2026
- National Park Service, Guidelines on Flood Adaptation for Rehabilitating Historic Buildings (2021)Read October 29, 2026
Next step
If you are planning foundation work on a historic house
Describe the house, the street it is on, and the work you are considering. You do not need to know whether it needs commission review.
Your request comes to NOLA Raised Home first. If it looks like a fit, we share it with one independent local provider, which decides whether it can help. Not every request is a match. We are not the contractor. How it works.